What a Commercial Kitchen Build-Out Really Costs, and What to Ask Before You Sign
Per-square-foot estimates vary widely, so know what each figure includes, how your starting space changes the price, and which approvals and bids to check first.

So you are staring at a vacant storefront and wondering what it will actually take to turn it into a working kitchen. Before you sign a lease or sign a contract, it helps to know the typical numbers, what sits inside them, and what tends to get left out. This guide walks through it in order. It is general information only, not personal financial, legal or medical advice, so check specifics with licensed professionals in your area.
A low per-square-foot number often just means more items were left out of the quote.

What a Build-Out Typically Costs
Published 2026 guides put commercial kitchen construction at roughly $250 to $500 per square foot, and that figure often excludes equipment. For a 1,000-square-foot kitchen, that means about $250,000 to $500,000 for construction alone. Add equipment and the total can land near $400,000 to $700,000 or more. Across all kinds of food-service spaces, whole projects range from about $40,000 to well over $1 million.
Restaurants run higher because they include dining areas and finishes. One 2026 benchmark put full-service restaurant build-outs at about $380 per square foot nationally, up roughly 28% since 2022. Contractor-published ranges by concept look like this:
- Ghost kitchen: about $275 to $450 per square foot
- Quick-service: about $325 to $525
- Fast-casual: about $375 to $625
- Full-service casual: about $425 to $725
- Upscale or chef-driven: about $550 to $900 or more
Location matters a great deal. Urban markets such as New York City, Los Angeles and Miami can run 40% to 60% higher than suburban or rural areas. These are contractor estimates, not verified prices, and costs vary by state and situation. Local bids will tell you more than any national average.
Where the Money Goes
The biggest single category is often kitchen mechanical, electrical and plumbing work. Hoods, fire suppression, refrigeration, gas lines, water service, grease handling and electrical capacity together make up about 28% to 38% of a typical fast-casual construction budget. A bigger hood can mean more airflow, more make-up air, and changes to HVAC, electrical service and even the roof.
Equipment is a separate bucket, commonly 30% to 40% of a renovation budget. Typical price ranges include:
- Combi ovens: $15,000 to $75,000
- Walk-in refrigeration: $25,000 to $85,000
- Blast chillers: $20,000 to $45,000
- Commercial dishwashers: $12,000 to $35,000
Skilled trades often account for 25% to 35% of renovation expenses, and certified installers in metro areas may charge about $85 to $125 per hour. Then there are costs that live outside the construction contract: design fees, point-of-sale systems, signage and smallwares. Closure matters too. One guide estimates fine-dining operations can lose $8,000 to $35,000 per day while closed. Once everything is counted, a renovation budget can roughly double.
How Starting Condition Changes the Price
Ask first: what is the space today? A raw shell needs the most work. A cold shell has some utilities in place. A second-generation space, one that already housed a food business, can save roughly 30% to 50% over a raw shell because the kitchen infrastructure is partly there. Chicago contractor data shows the spread well: a cosmetic refresh at $150 to $250 per square foot, a second-generation retrofit at $300 to $450, and a vanilla shell at $500 to $700 or more.
Do not assume a second-generation space is cheap, though. The health department may still require a new water heater, grease traps and backflow preventers, and an older fire suppression system may need a full overhaul. Older buildings also often lack the gas service a commercial kitchen needs, and utility upgrades can add weeks. Confirm what your local authority will require for that exact space before counting on savings.
How the Process Affects Cost and Timing
Several approvals come before a single wall goes up. Health department plan review, fire marshal approval and grease interceptor sizing are typically required. The authority having jurisdiction, often shortened to AHJ, prescribes the interceptor, and an exterior unit can mean site work, paving and easement coordination.
Layout is shaped by health-code finishes too. Think of these as the usual checklist:
- FRP wall panels and coved base
- Smooth ceilings
- Hand-sink placement
- Ware-washing layout
Miss them early and you pay for redesign. Pick equipment late and you may redo rough-in for plumbing, electrical and gas. A typical restaurant timeline runs 6 to 11 months: design 8 to 14 weeks, permitting 4 to 10 weeks, construction 12 to 22 weeks, and inspections and opening 2 to 3 weeks. Major equipment lead times should be mapped onto that calendar.
How to Compare Bids and What to Ask
Line up bids with the same scope and the same starting condition, or the comparison means nothing. Then work through these questions:
- What does the per-square-foot price include? Does it cover the general contractor fee, insurance and bonds? Are equipment, design, POS, signage and smallwares excluded?
- Can I get an itemized budget? Hood systems, grease handling, fire suppression, plumbing and equipment rough-in should each be a separate line. Bay Area contractor examples show how wide these can be: hoods at $15,000 to $50,000 and commercial plumbing at $20,000 to $60,000.
- Has feasibility for hood, grease and gas been confirmed with the AHJ before the lease is signed?
- Who pays for gas service, grease systems and hood penetrations, landlord or tenant? Get it in writing, and have an attorney review the lease.
- How long are equipment lead times, and when should I order?
- Does the budget include closure costs and lost revenue during the work?
Red Flags to Watch For
Be wary of a very low per-square-foot figure that does not say what is included or what the space looked like when priced. Missing MEP work, permits, equipment or contingency tends to come back later as change orders.
Also look for budgets with no line for utility upgrades, grease interceptors, fire suppression or health-code finishes, especially in an older building. A contractor who cannot explain how the design will satisfy the AHJ, or who leaves permitting time out of the schedule, is another warning sign. Verify requirements yourself with your local health department, fire marshal and building officials, and consider a licensed professional for advice on your own project.
Sources
- Commercial Kitchen Construction Cost: 2026 Guide
- Commercial Kitchen Buildout Cost Bay Area 2026 | Custom Home
- Restaurant Construction Cost Per Square Foot in 2026
- Restaurant Buildout Cost Bay Area 2026 - Complete Pricing Guide | Custom Home
- Restaurant Build-Out Cost Chicago: 2026 Pricing Guide | Klasik | Klasik Construction
- Commercial Kitchen Renovation Cost Guide (2026)
- Restaurant Construction Costs 2026: QSR to Fine Dining Breakdown | Buildermuse
- Restaurant Buildout Cost Guide: What Restaurant Owners Should Budget For - Builders Group Construction BGC
Still have a question?
Related guides
-
Fixed or Variable: How to Choose a Business Electricity Contract Without Getting Caught Out
A practical checklist for comparing quotes, avoiding the costly rollover to a deemed rate, and asking the right questions before you sign. -
What Happens to Your Business Energy Bill When the Contract Ends
Letting a fixed-term energy contract lapse can quietly move your account to a much higher default rate, so knowing your end date, opt-out deadline and state rules matters. -
How to Read a Commercial Electric Bill, Section by Section
Supply, delivery and demand charges each answer a different question, and knowing which is which helps you spot errors and compare providers on total cost.