How Change Orders Work and How to Keep Them Under Control
A written, signed change order is the routine way to alter a construction contract, and knowing what it should contain helps you avoid surprise costs.

Ever had a contractor say, "While we're in here, we could..." and felt your budget tighten? That sentence is usually how a change order begins. A change order is the written, signed way to alter a construction contract's scope, price, or schedule without rewriting the whole agreement. Handled well, it is a routine piece of paperwork. Handled badly, it is where surprise costs come from. This guide walks through how the process works, what it tends to cost, and how to keep control of it. It is general information only, not legal or financial advice, so check anything specific with a licensed professional in your state.

What a change order is and why it exists
A change order is a written, signed modification to an existing contract. It keeps the record of the job accurate as the project evolves. On projects using the AIA A201-2017 General Conditions, it is signed by the owner, the contractor, and the architect where one is involved. It states the agreed change, the adjustment to the contract sum, and any adjustment to contract time.
Many people assume change orders only happen when someone makes a mistake. That is not the usual story. Most come from a short list of causes:
- Owner-directed changes, such as upgrading a countertop or adding an outlet.
- Hidden or differing site conditions found once walls or floors are opened.
- Delays outside anyone's control, like weather.
- New code or permit requirements.
The written part matters. In California, a home improvement contract over $500 must be in writing, and changes to it must be in writing too. Verbal changes are described as not enforceable there. A spoken promise on a busy job site is a weak substitute for paper.
What a proper change order contains
Before you sign anything, check that the document answers the basic questions. A complete change order usually includes:
- The project name, contract number, a sequence number, and dates.
- A detailed description of the change and the reason for it.
- Itemized pricing: labor, materials, permit costs, and markup.
- The schedule impact, plus the updated contract total and completion date.
- Signatures from both parties.
On AIA projects, the G701-2017 form records the original contract sum, the net change from earlier change orders, the new contract sum, the change in days, and the new substantial completion date. Both sides should sign only after they agree on cost and time. Itemizing is what lets you compare the charge to the work you actually see.
The original contract should also say who obtains permits and what the completion date is. A change that touches either one is a common source of disputes, so it helps to know the baseline before the change arrives.
What change orders typically cost
Costs vary by state, trade, and the specifics of your house, so treat every number here as a planning range. One industry source estimates that change orders account for 7 to 15 percent of total project costs, and says up to 80 percent of construction projects see cost overruns. Those are broad figures, not predictions for your job.
A California homeowner guide suggests planning for 5 to 15 percent of project cost in change orders on a healthy job. It also suggests holding a 15 to 20 percent contingency in the budget. On a $60,000 remodel, that means setting aside roughly $9,000 to $12,000 you hope not to spend.
The same guide, written by a single contractor, offers example California ranges. They are not verified against a government source, so use them only to get a feel for scale:
- Moving a non-load-bearing wall: about $3,000 to $7,000.
- Adding a window: about $2,400 to $5,400.
- Replacing knob-and-tube wiring, per room: about $3,600 to $8,500.
- Small-area asbestos abatement: about $4,200 to $11,000.
One more detail: a change can add days as well as dollars. Ask how schedule delays will be priced, not only the direct labor and materials.
How to choose a contractor who handles changes well
The best protection against messy change orders is built before work starts. Read the original contract with these checks in mind:
- Scope: Is it detailed, with materials, model numbers, and who does which task? Vague scope is the most common root of later disputes.
- Markup: Is the percentage on change work written into the contract? Settling it now means you will not be negotiating under pressure later.
- Payment schedule: Is it detailed and in writing? Under California rules, payments generally may not exceed the value of work performed, apart from a down payment.
- Tracking: Can the contractor explain how changes are logged and who approves them?
A contractor who answers these calmly and specifically is usually one who has a system. Hesitation here tells you something too.
Questions to ask before you sign
Bring a short list to the contract meeting and write the answers down:
- Will every promise, including verbal ones, be written into the contract? If it is not on paper, you may have no practical way to enforce it.
- How will change orders be priced, and what is the markup percentage? Ask for the number in writing.
- How will schedule impacts be recorded, and how is the updated completion date set?
- Who approves change orders, and what dollar thresholds require my sign-off before work begins?
- Can we review the change order log together on a regular schedule?
That last question is a quiet favorite. A weekly look at the running total keeps small additions from piling up unnoticed.
Red flags to watch for
Most trouble shows up in a few recognizable ways:
- The contractor does the work first and hands you the change order afterward. You lose the chance to approve the cost before it exists.
- Change orders arrive without itemized labor and material costs.
- Descriptions are too vague to check against the work.
- Changes are agreed only verbally, or promises made mid-job never reach the page.
If you see any of these, pause new work and ask for a written, itemized change order before anything proceeds. Pausing feels awkward. It is cheaper than a disputed bill.
What this guide does not cover
Rules differ by state, and this guide leans mainly on California sources. Check your own state's contractor licensing and contract requirements. For California specifics, the state licensing board publishes a home improvement contract overview. For how the standard forms work, the AIA offers a plain explanation of change order fundamentals.
Cancellation rights, dispute resolution, arbitration, and what to do if a contractor refuses a written change order are not covered here. Neither are permit and licensing rules beyond the point that the contract should say who pulls permits. Your state licensing board or consumer protection office, or a licensed attorney, is the right place to ask.
Sources
- Learn About Home Improvement Contracts - CSLB
- https://vertexaisearch.cloud.google.com/grounding-api-redirect/AUZIYQGejhb2BCHykBPMfi0fzxUHTbSD27l8mp6djaVatXl_RXz0j49aTgLDLb2UA2lINOeAzybL3Hb-IO4ghKF-kD_JLUu74ETH8C_9mmT5nYHqAtUFaSaPZ7PYUTsqHkekVR8-ylsBne0utfBAXwjz06TCf9zp85uRyO3632JgIV3rkaFNMpgRzwrVknHumP0rV6I5
- AIA Change Order Form: Guide to the G701 Change Order | Procore
- Instructions: G701™–2017, Change Order
- Construction Change Orders: Fundamentals, Process & Forms | AIA Contract Documents
- Construction Change Orders: California Homeowner's Guide | MY Cali BUILDERS
- Why late-stage cost overruns are symptoms of a larger problem | Construction Dive
- 5 Ways to Reduce Construction Cost Overruns Effectively | Linarc
Still have a question?
Related guides
-
Upgrading to 200 Amps Without the Surprise Bill
Panel costs are only part of the story, so here is what a 200 amp upgrade typically runs, what can get added on, and what to ask before you sign. -
Tank or Tankless? How to Compare Water Heater Bids on Equal Terms
Learn how tank and tankless units differ, and which details a written plumber's quote should spell out so three bids can be compared fairly. -
Find the Water First: A Practical Guide to Deciding on Mold Testing and Cleanup
Before anyone runs a sample or quotes a job, the moisture source and the size of the visible patch settle most of the decision.